Attend market Kickoff
-
Convey information to the station
Complete Inventory
Coordinate initial station inventory – internal/external
Conduct initial station inventory
Prepare inventory for online data entry
Enter inventory into online Nextel tool
Facilitate submission of inventory to Nextel
Equipment Validation
-
Inventory Validation
-
Coordinate resources for inventory validation by Sprint Nextel vendor
-
Manage the Nextel vendor validation
-
Review Nextel reconciled inventory
-
Process the reconciliation of the final inventory internally and with Sprint Nextel
-
Facilitate Equipment and Service Integrator station (Group) requirements
Compensation Agreement
-
Utilize final Inventory to begin quote gathering process
-
Coordinate the resources to facilitate the selection of
-
Vendors
-
Equipment
-
Service Integrator(s)
-
-
Facilitate the internal cost estimates requirements
-
Make recommendations for final relocation costs estimates
-
Supervise the overall completion of the required quotes and estimates
Equipment Order
-
Facilitate the internal Purchase Order (PO) generation process
-
Review the PO against the Relocation Agreement
-
Process the PO to Nextel requirements
-
Track and assist in vendor invoicing
-
Track and assist in Nextel invoicing
Vendor Fulfillment
-
Track vendors fulfillment progress
-
Coordinate service integrators for station
-
Setup in market training with SignaSys
-
Setup in station training with SignaSys
-
Facilitate station training
-
Facilitate new FCC Licensing requirements
-
Reconcile received orders against PO
-
Notify Sprint Nextel of equipment fulfillment issues; for Vendor Payment Release
Equipment Installation
-
Manage the overall installation process
-
Coordinate the service integrators
-
Supervise the installation process
-
Conduct systems controls
-
Inspect installation for 100% compliance
-
Manage the “Narrowed in Place” system cut-over
-
Signoff on final installation requirements
-
Review 3rd party invoices
-
Review and track internal costs and personnel
-
Process internal invoices
-
Process vendor invoicing
-
Reconcile invoicing with Sprint Nextel auditors
-
Setup narrow in place systems training
Channel Relocation
-
Coordinate with Sprint Nextel and market stations for the Retune Weekend
-
Facilitate the station cutover
-
Sign off on cutover acceptance
Market Closeout
-
Determine that all relocation efforts have been performed to stations expectations and contractual requirements
-
Pack and ship retired 2GHz equipment to Sprint Nextel warehouse in Texas
-
Finalize new channel plan licensing issues
-
Process final invoicing and approvals
-
Process information for Sprint Nextel payments
-
Reconcile final invoices with Sprint Nextel Auditors
-
Review any discrepancies with station and open negotiations with Sprint Nextel if any overages
-
Close out project paperwork and project plan